Reading: Vandalism of transmission towers surge, as TCN records 6 incidents in 5 months
Share
Sign In
Notification Show More
Font ResizerAa
Advisors ReportsAdvisors Reports
Font ResizerAa
Search
  • News
  • Editorial
  • Feature
  • Special Report
  • Oil & Gas
    • Upstream
    • Midstream
    • Downstream
  • Power
    • Generation
    • Distribution
    • Transmission
  • Renewables
    • Solar
    • Nuclear
    • Hydrogen
  • Extractive Industry
  • Maritime
Have an existing account? Sign In
Follow US
© 2022 Foxiz News Network. Ruby Design Company. All Rights Reserved.
DistributionImpactNewsPowerSabotageTransmission

Vandalism of transmission towers surge, as TCN records 6 incidents in 5 months

Admin
Last updated: April 23, 2024 1:27 pm
Admin
Share
5 Min Read
TCN Vandalised Transmission Line
SHARE

 

… vandals strike four towers along Jos-Gombe 330kV transmission line on Monday

 

…. third time’s the charm: Gombe’s connecting transmission line hit again

 

Oredola Adeola

Nigeria has recorded a surge in incidents of vandalism of transmission lines, with five significant incidents reported in the first quarter of 2024 alone and one recorded in December 2023, including the recent destruction of four towers along the Jos-Gombe 330kV transmission line by vandals on Monday, April 22, 2024.

 

According to the Transmission Company of Nigeria (TCN) four towers (288, 289, 290, and 291 ) along the Jos-Gombe 330kV transmission line were damaged by vandals on Monday, April 22, 2024, around 3:32 pm, resulting in the disruption of bulk power supply to the Gombe, Yola, and Jalingo Substations and affecting the supply to parts of the Yola and Jos Electricity Distribution Companies’ franchise areas.

 

Ndidi Mbah, TCN General Manager, Public Affairs, confirmed this in a statement obtained by Advisors Reports on Monday.   

 
TCN explained in the statement that when the 330kV transmission line tripped, its operators attempted to restore it to service, but it tripped again, prompting the dispatch of TCN lines men to trace the line in order to detect and rectify the fault.

Mbah said, “While fault tracing, TCN’s engineering crew discovered that towers 288, 289, 290, and 291 were vandalised and that some tower members were carted away.  Also, the towers had equally collapsed as a result of the incident.”

She therefore noted that the bulk power supply to Gombe, Yola, and Jalingo Substations was disrupted, affecting bulk power supply to parts of Yola and Jos Electricity Distribution Companies’ franchise areas.
 

To mitigate the effect of the incident on electricity consumers affected by the incident, the TCN’s spokesperson emphasised that the company is trying to first backfeed Gombe through its 132kV transmission line from Bauchi and subsequently Ashaka, Potiskum, Damaturu, and Billiri/Savannah.
She therefore assured that TCN will do everything in its capacity to ensure that supply is restored to the affected areas, while efforts are made to reconstruct the four vandalised towers.
Advisors Reports’ check showed that these attacks which has happened predominantly in the Northern part of the country especially on the transmission lines connecting Gombe, are often carried out with explosives, leading to severe disruptions in power distribution and posing a serious threat to the stability of Nigeria’s power sector.

The trajectory of vandalism as gathered by Advisors Reports includes:

December 21, 2023: Towers T372 and T373 along the Gombe-Damaturu 330kV Single Circuit transmission line was brought down.

February 1: Tower 388 along the Jos-Bauchi 132kV Single Circuit transmission line was vandalized, leading to a power outage in Yobe and Borno States.

February 23: Two transmission towers, T377 and T378, along the Gombe-Damaturu 330kV transmission line were destroyed by vandals, resulting in a load loss of approximately 5MW.

February 26: Tower 70 along the 330kV Gwagwalada-Katampe transmission line was vandalized, reducing bulk power supply flexibility and the volume of power into Abuja by 250MW.

March 10: The Shiroro-Katampe 330 Kilo Volt (kV) transmission line was vandalized, the fifth such incident between February and March.

 

These acts of vandalism which has taken a new form, have significantly reduced bulk power supply flexibility and the volume of power in affected states, causing discomfort to residents who rely on these infrastructures.

 

Adebayo Adelabu, Minister of Power, has in a recent statement recommended capital punishment for any offender arrested in connection with the practice.

 

The TCN on its part, has also secured the support of the Office of the National Security Adviser and other Security Agencies to ensure the safety and security of its installations.

 

Stakeholders have called for sensitization on the culture of protecting public assets, coupled with stiffer penalties for vandals, as deterrence.

 

The Nigerian Society of Engineers (NSE) and the Association of Professional Women Engineers of Nigeria (APWEN) for instance have urged the government to strengthen enforcement of existing laws to deter vandalism, treat such acts as a criminal offense, and invest in newer technologies that can help detect and prevent vandalism.

 

 

 

 

Ogbechie,GMD Rain Oil, Okulaja-Kotun ,VC CORAN call for full deregulation of petrol pricing, demand fair market practices
Outrage as Power Minister allegedly bypasses due process in N40bn metering project deal awarded to De Haryor Global Service
DisCos fail to recover ₦125.7bn in two months despite ₦496bn customers’ billing
President Tinubu approves N10bn for CNG buses, N50,000 monthly for 100,000 families in each state
Experts at #NOGOF2025 identify indigenous capacity, technology as cornerstone for Nigeria’s energy future

Sign Up For Daily Newsletter

Be keep up! Get the latest breaking news delivered straight to your inbox.
[mc4wp_form]
By signing up, you agree to our Terms of Use and acknowledge the data practices in our Privacy Policy. You may unsubscribe at any time.
Share This Article
Facebook Copy Link Print
Share
Previous Article NERC activates Electricity Act, transfers regulatory oversight of electricity market in Enugu State to EERC
Next Article Ekiti State Govt takes over electricity market oversight from NERC
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

- Advertisement -
Ad imageAd image

Latest News

 Lagos-Calabar coastal highway: Tinubu warns developers on corridor setbacks
Concession Documentary Impact News Special Project Sustainability
May 31, 2025
Nigeria’s terrorism war shaken by internal sabotage, foreign complicity amid Tinubu’s midterm celebrations
Documentary Editorial Security Special Project Technology
May 30, 2025
Nigeria’s KGG hub wins IGUs regional gas award at WGC 2025 
Documentary Midstream Oil & Gas Sustainability Technology
May 28, 2025
NUPRC receives Final Engineering Audit report on upstream measurement equipment from PE Energy
Documentary News Oil & Gas Special Project Sustainability Upstream
May 27, 2025
Follow US
© 2022 AdvisorsReports. All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?