Reading: National grid collapses for 7th time in 2024, as supply drops to 0MW
Share
Sign In
Notification Show More
Font ResizerAa
Advisors ReportsAdvisors Reports
Font ResizerAa
Search
  • News
  • Editorial
  • Feature
  • Special Report
  • Oil & Gas
    • Upstream
    • Midstream
    • Downstream
  • Power
    • Generation
    • Distribution
    • Transmission
  • Renewables
    • Solar
    • Nuclear
    • Hydrogen
  • Extractive Industry
  • Maritime
Have an existing account? Sign In
Follow US
© 2022 Foxiz News Network. Ruby Design Company. All Rights Reserved.
DistributionNewsPowerTransmission

National grid collapses for 7th time in 2024, as supply drops to 0MW

Admin
Last updated: April 15, 2024 1:30 pm
Admin
Share
3 Min Read
SHARE

… makes gradual recovery from 64.7MW around 3am to 880MW at Monday noon

…TCN blames collapse on fire incident at Afam Power generating station

 

Oredola Adeola

The national electricity grid suffered its seventh grid collapse in 2024, around 2:00 am on Monday, with generation dropping to zero from 2,583.77MW and later partially recovering to 64.7MW around 3 am, followed by a steady recovery that has led to a load allocation of 880MW to Discos as of 11:58 am on the same day.

 

The Independent System Operator, an arm of the Transmission Company of Nigeria, (TCN) data of the electricity distribution companies (DisCos), reviewed by Advisors Reports showed that the 800MW allocated to the 11 Distribution Companies (DisCos) was shared as follows:

 

Abuja Disco had 100.00 MW, Benin Disco 80.00 MW, Eko Disco 50.00 MW, Enugu Disco 50.00 MW, Ibadan Disco 150.00 MW, Ikeja Disco 150.00 MW, Jos Disco 50.00 MW, Kaduna Disco 50.00 MW, Kano Disco 90.00 MW, PHarcourt Disco 70.00 MW, and Yola Disco 40.00 MW.

 

The active fifteen (15) power plants gradually recovered and restored electricity supply as Ibom Power Plant made the first recovery around 3am with 64.70MW, but the power output fluctuated throughout the morning, dropping to 44.50MW around 4 am and later moving up to 53.60MW at Monday noon.

 

The Shiroro (Hydro) and Jebba (Hydro) joined the recovery efforts around 5 am and 10 am, contributing 82.99MW and 160MW, respectively.

 

Okpai (Gas/Steam) and Azura-Edo IPP (Gas) also joined the fray, contributing 117MW and 93MW around 11 am and 6 am, respectively.

 

Geregu (Gas) and Olorunsogo (Gas) also made a comeback around 9 am and 10 am, contributing 90MW and 32.20MW, respectively.

 

CAUSE: Fire incident at Afam Power generating station

 

Ndidi Mbah, TCN General Manager, Public Affairs, in a statement obtained by Advisors Reports disclosed that announced the full restoration of the national grid following a fire incident at the Afam power generating station, which caused a partial disturbance of the nation’s grid.

According to her at 02:41am on Monday, April 15, 2024, a fire erupted at the Afam V 330kV bus bar coupler, leading to the tripping of units at Afam III and Afam VI.

 

She said, “This resulted in a sudden generation loss of 25MW and 305MW respectively, destabilizing the grid and causing a partial collapse.

“During the incident, the Ibom Power plant was isolated from the grid and was supplying parts of the Port Harcourt Region. This further minimized the effect of the system disturbance,” Mbah said.

 

TCN further confirmed that the affected section of the grid has been fully restored and stabilized, reaffirming its commitment to enhancing the resilience and reliability of the national grid.

 

 

 

SPDC deploys Uncrewed Surface Vessel (USV) for pipeline route survey in Niger Delta
Federal High Court sentences 4 Chinese nationals to 20 years’ imprisonment for illegal mining in Plateau
Min. of Petroleum endorses 3rd edition of gas investment forum 2025
NCDMB’s Obinna Ezeobi unveils book on local content, strategic communication journey
Mainstream Energy invests $82m to install 1G3, 1G4, boosting Kainji hydropower plant capacity to 980MW

Sign Up For Daily Newsletter

Be keep up! Get the latest breaking news delivered straight to your inbox.
[mc4wp_form]
By signing up, you agree to our Terms of Use and acknowledge the data practices in our Privacy Policy. You may unsubscribe at any time.
Share This Article
Facebook Copy Link Print
Share
Previous Article SPDC deploys Uncrewed Surface Vessel (USV) for pipeline route survey in Niger Delta
Next Article NDDC sets April deadline for Inauguration of 132/33kv sub-station in Ode-Erinje, Okitipupa
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

- Advertisement -
Ad imageAd image

Latest News

Sanwo-Olu swears in Odubiyi, 4 others as pioneers of Lagos Electricity Regulatory Commission
Distribution Energy Transition Generation News Power Transmission
May 21, 2025
AMMON backs Tinubu’s ‘Nigeria First Policy’, says it will unlock Nation’s industrial potential
Distribution Local Content News Power Technology
May 19, 2025
11 Plc approves ₦3.34bn final dividend for FY 2024, declares 925 Kobo per share
Documentary Downstream Finance Gas Green Finance Impact Midstream News Oil & Gas Special Project
May 19, 2025
FG approves revival of Ikere Gorge Hydropower plant, construction of new substation for Oyo State
Distribution Energy Transition Hydroplant News Power Renewables Transmission
May 15, 2025
Follow US
© 2022 AdvisorsReports. All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?