Reading: Gov Aiyedatiwa of Ondo assures completion of 30 MW tri-fuel power plant in Ore after 12-year delay
Share
Sign In
Notification Show More
Font ResizerAa
Advisors ReportsAdvisors Reports
Font ResizerAa
Search
  • News
  • Editorial
  • Feature
  • Special Report
  • Oil & Gas
    • Upstream
    • Midstream
    • Downstream
  • Power
    • Generation
    • Distribution
    • Transmission
  • Renewables
    • Solar
    • Nuclear
    • Hydrogen
  • Extractive Industry
  • Maritime
Have an existing account? Sign In
Follow US
© 2022 Foxiz News Network. Ruby Design Company. All Rights Reserved.
DistributionGenerationLocal ContentNewsPower

Gov Aiyedatiwa of Ondo assures completion of 30 MW tri-fuel power plant in Ore after 12-year delay

Admin
Last updated: August 26, 2024 11:45 pm
Admin
Share
2 Min Read
SHARE

Oredola Adeola

Governor Lucky Aiyedatiwa of Ondo State has reaffirmed his commitment to bringing the 30 MW Tri-Fuel turbine power plant located along the Ore-Sagamu Expressway in Ore to fruition, after 12 years being on under construction.

Comrade Allen Sowore, Senior Special Adviser to the Ondo State Governor on Strategic Communication, made this known in a statement obtained by Advisors Reports on Sunday.

According to Sowore, Governor Aiyedatiwa gave the assurance on Sunday, August 25, 2024, when he conducted a facility tour of the 30 MW Turbine Power Plant established in 2012 by former Governor Dr. Olusegun Mimiko.

Governor Aiyedatiwa reaffirmed his commitment to bringing this significant project to fruition, emphasizing the substantial investment by previous administrations.
“What is required now is to allocate a little more resource and commit ourselves to ensuring that the project becomes operational. And I am sure God will see us through,” he said.
 Engr. Ayodele Ikumapayi, President / CEO at ASB VALIANT Group, the contractor in charge of the project, who accompanied the governor, in his remark during the inspection, stated that the power plant is solely owned by the state government.
He explained that once completed, the plant will have the capacity to serve the entire Ore area and its surroundings, including the Industrial Park.
Advisors Reports reveal that the Ondo State Government-owned plant, with an installed capacity of 30MW from its Tri-Fuel Gas Turbine (15+15), is the first power plant in Africa to utilize natural gas, liquefied petroleum gas, and diesel, and is now ready for commissioning.

 

TCN energizes 25 transmission transformers, boosts capacity to 2150 MVA between January, June 2024 – Engr. Abdulaziz, TCN MD
#AEW2024: Tinubu’s Energy Adviser calls for transformative shifts in Africa’s workforce
NNPC boss, Kyari hits 60, praises Tinubu, Buhari
Nigeria LNG unveils new logo, reaffirms commitment to sustainable future
Dr. Sophia Horsfall appointed NLNG GM, External Relations and Sustainable Development as Andy Odeh retires

Sign Up For Daily Newsletter

Be keep up! Get the latest breaking news delivered straight to your inbox.
[mc4wp_form]
By signing up, you agree to our Terms of Use and acknowledge the data practices in our Privacy Policy. You may unsubscribe at any time.
Share This Article
Facebook Copy Link Print
Share
Previous Article NNPCL launches LNG shipments to Japan, China on DES basis, boosts global supply footprint 
Next Article Transmission towers vandals persist despite arrests, as TCN confirms another incident in Osun State
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

- Advertisement -
Ad imageAd image

Latest News

AMMON backs Tinubu’s ‘Nigeria First Policy’, says it will unlock Nation’s industrial potential
Distribution Local Content News Power Technology
May 19, 2025
11 Plc approves ₦3.34bn final dividend for FY 2024, declares 925 Kobo per share
Documentary Downstream Finance Gas Green Finance Impact Midstream News Oil & Gas Special Project
May 19, 2025
Federal High Court sentences 4 Chinese nationals to 20 years’ imprisonment for illegal mining in Plateau
Documentary Environment Extractive Industry Mining News Sabotage
May 16, 2025
FG approves revival of Ikere Gorge Hydropower plant, construction of new substation for Oyo State
Distribution Energy Transition Hydroplant News Power Renewables Transmission
May 15, 2025
Follow US
© 2022 AdvisorsReports. All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?